Henry Wadsworth Longfellow School was a 1960s box that had been modified in piece-meal fashion for over 35 years. As part of a district-wide plan, the school had been scheduled for renovation in order to meet the district's changing needs. GreenAssociates worked with the district and the schools staff to help define their needs and to develop a coherent, effective plan as the school district prepared to enter the 21st century. |
|
The existing nondescript entry was relocated to the center
of the building, flanked by decorative lighting and marked by a high
cupola. Circulation was simplified
and redirected from the learning center's core, which had been very
disruptive to the perimeter.
Carpeting patterns define learning areas to further direct
circulation.
|
|
|
|
|
|
|
|
|
|
|
|
Grades K-5 Final Cost Estimate $2,270,048 Change Orders* 5.7% Total Construction Cost $2,116,526 Completion Date Dec. 1996 |
||
|
|
|
*Approx. 1.5% due to Owner added construction |
||